Construction of a sea pipeline from Siri Island to Asalouyeh Port

Construction of a sea pipeline from Siri Island to Asalouyeh Port

Employer: Petroleum Engineering and Development Company (PEDEC), Iranian Offshore Oil Company (IOOC) Project Status: Completed

Project Summary :  This pipeline is the longest gas transmission pipeline from the offshore sector to the onshore facilities of South Pars in Asalouyeh port.

The 32-inch gas pipeline from Siri Island to Asalouyeh Port is 305 kilometers long, the longest sea pipeline in the Persian Gulf, which includes 290 kilometers of pipelines in the sea and about 15 kilometers of pipelines on the coast.
Project start date: 2008
Type of contract: EPC
Project goals: Daily transfer of 530 million cubic feet of gas received from Salman Field from Siri Island to the gas processing facility in Asalouyeh port.
Completed works:
    - Carrying out survey operations, basic and detailed design
    - Construction of 290 kilometers of a 32-inch sea pipeline
    - Construction of 15 kilometers of a 32-inch pipeline in the coast
    - Manufacture and installation of a manifold in Asalouyeh

tags projects
The South Pars oil layers development project started in 2004 with the aim of producing 25,000 barrels/day of crude oil.
At the present a subsidiary company of Petroiran ,on behalf of Petroiran company has entered into contract with Iranian Offshore Oil Company (IOOC)...
Construction and installation of infrastructures (jackets) and pipelines in Forouzan Fields which started in 2008.
The Salman field development project started in 2000 with the aim of increasing oil production by 50,000 barrels per day and producing 540 million cub...
The development plan of Forozan and Esfandiar fields started in 2002 with the aim of increasing oil production by 50,000 b/d.
The development plan of Jofeir Oil Field started in 2008 with the aim of early production of 3,500 barrels/day of crude oil and 1.7 million cubic feet...
The Azadegan oil field development project started in 2003 with the aim of early production of 50,000 barrels of oil per day.
The development plan of Nusrat and Farzam fields started in 2000 with the aim of increasing oil production by 16,450 barrels per day.
Construction of the Middle East’s first FPSO by Petro-Iran Development Company
The project started in 2005 with the aim of developing the gas field by drilling an appraisal well and providing ancillary services.
The project contract was signed in 2013 with the aim of drilling and completing 11 appraisal and development gas wells.
Providing integrated drilling services for 10 drilling rigs operated by Iranian Offshore Oil Company (IOOC)
Providing integrated drilling services for 15 offshore drilling rigs and 3 onshore drilling rigs operated by IOOC
The project started in 2015 with the aim of increasing the capacity of Abuzar gas transmission to Darood II facility in Kharg Island
The project started in 2018 with the aim of increasing production from the wells by 16,000 b/d
Address : No. 20, Tabrizian st, Dastgerdi (Zafar) St., Shariati Ave., Tehran-Iran
Tel : +98-21-22914811 - 18
Fax : +98-21-22914798
Address : No. 20, Next To Shahid AmirSoheil Tabrizian Alley, Shahid Dastgerdi (Ex Zafar) Street, Shariati Street,
Tel : +98-21-22914811 - 18
Fax : +98-21-22914798
Address : No. 20, Next To Shahid AmirSoheil Tabrizian Alley, Shahid Dastgerdi (Ex Zafar) Street, Shariati Street,
Tel : +98-21-22914811 - 18
Fax : +98-21-22914798
qrcode
© copyright 2018 Petroiran. All rights reserved
Design By ParsianGroup.com