The Koroosh FPSO is the first processing vessel built in the Middle East and has recovery, processing and desalination systems for extracted crude oil with the ability to store and load.
Project start date: 2014
Type of contract: EPCIC
Completed Works: Engineering, procurement, construction, installation and operation of an FPSO with the following specifications:
- Crude oil processing capacity at 35,000 barrels per day
- Water injection capacity at 60,000 barrels per day
- Storage capacity of 714,000 barrels
- Loading capacity of 700,000 barrels