Supply and construction of a floating production storage and offloading (FPSO)

Supply and construction of a floating production storage and offloading (FPSO)

Employer: Pars Oil and Gas Company Project Status: Completed

Project Summary :  Construction of the Middle East’s first FPSO by Petro-Iran Development Company

The Koroosh FPSO is the first processing vessel built in the Middle East and has recovery, processing and desalination systems for extracted crude oil with the ability to store and load.
Project start date: 2014
Type of contract: EPCIC
Completed Works: Engineering, procurement, construction, installation and operation of an FPSO with the following specifications:
    - Crude oil processing capacity at 35,000 barrels per day
    - Water injection capacity at 60,000 barrels per day
    - Storage capacity of 714,000 barrels
    - Loading capacity of 700,000 barrels

tags projects
The South Pars oil layers development project started in 2004 with the aim of producing 25,000 barrels/day of crude oil.
At the present a subsidiary company of Petroiran ,on behalf of Petroiran company has entered into contract with Iranian Offshore Oil Company (IOOC)...
Construction and installation of infrastructures (jackets) and pipelines in Forouzan Fields which started in 2008.
The Salman field development project started in 2000 with the aim of increasing oil production by 50,000 barrels per day and producing 540 million cub...
The development plan of Forozan and Esfandiar fields started in 2002 with the aim of increasing oil production by 50,000 b/d.
The development plan of Jofeir Oil Field started in 2008 with the aim of early production of 3,500 barrels/day of crude oil and 1.7 million cubic feet...
The Azadegan oil field development project started in 2003 with the aim of early production of 50,000 barrels of oil per day.
This pipeline is the longest gas transmission pipeline from the offshore sector to the onshore facilities of South Pars in Asalouyeh port.
The development plan of Nusrat and Farzam fields started in 2000 with the aim of increasing oil production by 16,450 barrels per day.
The project started in 2005 with the aim of developing the gas field by drilling an appraisal well and providing ancillary services.
The project contract was signed in 2013 with the aim of drilling and completing 11 appraisal and development gas wells.
Providing integrated drilling services for 10 drilling rigs operated by Iranian Offshore Oil Company (IOOC)
Providing integrated drilling services for 15 offshore drilling rigs and 3 onshore drilling rigs operated by IOOC
The project started in 2015 with the aim of increasing the capacity of Abuzar gas transmission to Darood II facility in Kharg Island
The project started in 2018 with the aim of increasing production from the wells by 16,000 b/d
Address : No. 20, Tabrizian st, Dastgerdi (Zafar) St., Shariati Ave., Tehran-Iran
Tel : +98-21-22914811 - 18
Fax : +98-21-22914798
Address : No. 20, Next To Shahid AmirSoheil Tabrizian Alley, Shahid Dastgerdi (Ex Zafar) Street, Shariati Street,
Tel : +98-21-22914811 - 18
Fax : +98-21-22914798
Address : No. 20, Next To Shahid AmirSoheil Tabrizian Alley, Shahid Dastgerdi (Ex Zafar) Street, Shariati Street,
Tel : +98-21-22914811 - 18
Fax : +98-21-22914798
qrcode
© copyright 2018 Petroiran. All rights reserved
Design By ParsianGroup.com