Projects
Development of Nusrat and Farzam fields

Development of Nusrat and Farzam fields

Employer: Petroleum Engineering and Development Company (PEDEC) Project Status: Completed

Project Summary :  The development plan of Nusrat and Farzam fields started in 2000 with the aim of increasing oil production by 16,450 barrels per day.

Nusrat and Farzam oil fields are located 35 kilometers southeast of Siri Island in the Persian Gulf and are shared with the United Arab Emirates.
Project start date: 2000
Type of contract: Buyback 
Project Goals:
    - Enhancing oil production and reaching the maximum production rate of 16,450 barrels per day in Nusrat Field
    - Operation of the field with an initial production of 15,000 barrels of crude oil per day in the Farzam field
Completed Works:
    - Workover, completion and re-drilling of 4 wells and drilling and completion of a new well in Nusrat Field
    - Drilling a new multi-branch appraisal well in Farzam Field 
    - Interpretation of 3D seismic data and comprehensive study of the reservoir in Farzam Field

tags projects
The South Pars oil layers development project started in 2004 with the aim of producing 25,000 barrels/day of crude oil.
At the present a subsidiary company of Petroiran ,on behalf of Petroiran company has entered into contract with Iranian Offshore Oil Company (IOOC)...
Construction and installation of infrastructures (jackets) and pipelines in Forouzan Fields which started in 2008.
The Salman field development project started in 2000 with the aim of increasing oil production by 50,000 barrels per day and producing 540 million cub...
The development plan of Forozan and Esfandiar fields started in 2002 with the aim of increasing oil production by 50,000 b/d.
The development plan of Jofeir Oil Field started in 2008 with the aim of early production of 3,500 barrels/day of crude oil and 1.7 million cubic feet...
The Azadegan oil field development project started in 2003 with the aim of early production of 50,000 barrels of oil per day.
This pipeline is the longest gas transmission pipeline from the offshore sector to the onshore facilities of South Pars in Asalouyeh port.
Construction of the Middle East’s first FPSO by Petro-Iran Development Company
The project started in 2005 with the aim of developing the gas field by drilling an appraisal well and providing ancillary services.
The project contract was signed in 2013 with the aim of drilling and completing 11 appraisal and development gas wells.
Providing integrated drilling services for 10 drilling rigs operated by Iranian Offshore Oil Company (IOOC)
Providing integrated drilling services for 15 offshore drilling rigs and 3 onshore drilling rigs operated by IOOC
The project started in 2015 with the aim of increasing the capacity of Abuzar gas transmission to Darood II facility in Kharg Island
The project started in 2018 with the aim of increasing production from the wells by 16,000 b/d
Address : No. 20, Tabrizian st, Dastgerdi (Zafar) St., Shariati Ave., Tehran-Iran
Tel : +98-21-22914811 - 18
Fax : +98-21-22914798
Address : No. 20, Next To Shahid AmirSoheil Tabrizian Alley, Shahid Dastgerdi (Ex Zafar) Street, Shariati Street,
Tel : +98-21-22914811 - 18
Fax : +98-21-22914798
Address : No. 20, Next To Shahid AmirSoheil Tabrizian Alley, Shahid Dastgerdi (Ex Zafar) Street, Shariati Street,
Tel : +98-21-22914811 - 18
Fax : +98-21-22914798
qrcode
© copyright 2018 Petroiran. All rights reserved
Design By ParsianGroup.com